Academy St (N Braeswood to Merrick) Storm Sewer Relief Segment 1

Complete
General Contractor: Pace Services L. P.
COH Construction Project Manager: Joanne Kamman
SWMP Design Engr: RG Miller Engineers Inc.
Constr Est: $8,565,201.85
CIP No.: M-0255-2

 

What's Happening?

Construction started on 08-11-2008 and it should be completed within 585 calendar days.

Final Completion Inspection held on 11-19-09.

Substantial inspection held on 10-16-09.



Project Description

The project consists of storm sewer improvements including associated inlets, inlet leads, and laterals. The existing water lines throughout the project area will be upgraded and replaced. The pavement and sidewalks throughout the project area will be replaced in conjunction with a Neighborhood Street Reconstruction Project.

Last Updated 5/21/2010