This project is generally bounded by Interstate Highway 10 east Feeder Road on the North, Old Oaks Street on the South, West Bough Street on the West and Tallowood Street and Attingham Drive on the East. The project is located on Key Map 489-D and 489-H
Complete
General Contractor: Reytec Construction Resources Inc.
COH Constr PM: Joanne Kamman
SWMP Design Engr: Van De Wiele Engineering Inc.
Constr Contract: $16,274,537
CIP No.: M-0249-2
Construction started on 05-19-09 and it should be completed within 700 calendar days.
Final completion inspection held on 04-06-10.
Substantial completion inspection held on 01-29-10.
This project consists of the installation of approximately 5,915 linear feet of reinforced box storm sewer; 12,427 linear feet of 60-inch, 54-inch, 48-inch, 42-inch, 36-inch, 30-inch and 24-inch storm sewers; 2,275 linear feet of 10-inch and 6-inch sludge force main; 1,690 linear feet of 15-inch, 12-inch, 10-inch, 8-inch and 6-inch sanitary sewer; 5,820 linear feet of 54-inch, 15-inch, 12-inch, 10-inch, 8-inch and 6-inch sanitary sewer rehabilitation; 27,315 linear feet of 12-inch, 8-inch and 6-inch waterline; roadway reconstruction and sidewalk
Last Updated 5/21/2010