Fonn Villas / Memorial Area Storm Sewer Improvements

Complete
General Contractor: Reytec Construction Resources Inc.
COH Constr PM: Joanne Kamman
SWMP Design Engr: Van De Wiele Engineering Inc.
Constr Contract: $16,274,537
CIP No.: M-0249-2

 

What's Happening?

Construction started on 05-19-09 and it should be completed within 700 calendar days.

Final completion inspection held on 04-06-10.

Substantial completion inspection held on 01-29-10.





Project Description

This project consists of the installation of approximately 5,915 linear feet of reinforced box storm sewer; 12,427 linear feet of 60-inch, 54-inch, 48-inch, 42-inch, 36-inch, 30-inch and 24-inch storm sewers; 2,275 linear feet of 10-inch and 6-inch sludge force main; 1,690 linear feet of 15-inch, 12-inch, 10-inch, 8-inch and 6-inch sanitary sewer; 5,820 linear feet of 54-inch, 15-inch, 12-inch, 10-inch, 8-inch and 6-inch sanitary sewer rehabilitation; 27,315 linear feet of 12-inch, 8-inch and 6-inch waterline; roadway reconstruction and sidewalk

Last Updated 5/21/2010