The project area is generally bounded by Underwood Street to the south, Gramercy Street to the north, Buffalo Speedway to the east and Braes Boulevard to the west. The project is located in Key Map Grid 532-E, F, J, K.
Under Construction
General Contractor: Pace Services L. P.
Constr Est: $6,843,952
COH Construction Project Manager: Joanne Kamman
SWMP Design Engr: AECOM
Constr Award: FY2009
CIP No.:M-0253-2
Construction started on 06-22-09 and it should be completed within 475 calendar days
Construction is 80% complete as of progress meeting held on 05-04-10.
This project consists of approximately 10,346 linear feet of 66-inch, 42-inch, 36-inch, 30-inch, 24-inch storm sewers, 1,920 linear feet of 15-inch, 12-inch, 8-inch sanitary sewers, 15,773 linear feet of 8-inch waterline, and concrete roadway reconstruction with curb and gutter.
Last Updated 5/21/2010