Edloe St (Underwood to Gramercy) Storm Sewer Relief Segment 2

Under Construction
General Contractor: Pace Services L. P.
Constr Est: $6,843,952
COH Construction Project Manager: Joanne Kamman
SWMP Design Engr: AECOM
Constr Award: FY2009
CIP No.:M-0253-2

 

What's Happening?

Construction started on 06-22-09 and it should be completed within 475 calendar days

Construction is 80% complete as of progress meeting held on 05-04-10.

Project Description

This project consists of approximately 10,346 linear feet of 66-inch, 42-inch, 36-inch, 30-inch, 24-inch storm sewers, 1,920 linear feet of 15-inch, 12-inch, 8-inch sanitary sewers, 15,773 linear feet of 8-inch waterline, and concrete roadway reconstruction with curb and gutter.

Last Updated 5/21/2010