Bellaire West Drainage Improvements

Under Engineering Design
SWMP Design Engineer: CivilTech Enginners Inc.
Construction Award: FY2011
Construction Estimate: $4,765,000
CIP No.: M-0283

 

What's Happening?

Final QA/QC scheduled for 06-02-10.

90% Drawings received on 01-11-10 for review.

70% Drawings received on 08-24-09 for review.

50% Drawings received on 06-23-09 for review.

Project Description

The drainage improvements consist of new storm sewer along Stroud, Universal, and Carvel and at locations to be determined in Bellaire West Section Five subdivision. Street reconstruction, water line, and sanitary sewer replacement will occur when the new storm sewers are installed.

Last Updated 5/24/2010