Academy St (Merrick to Gramercy) Storm Sewer Relief Segment 2

Under Construction
General Contractor: JFT Construction
Constr Est: $6,545,156.50
COH Construction Project Manager: Joanne Kamman
SWMP Design Engr: R. G. Miller Engineers, Inc.
Constr Award: FY2010
CIP No.:M-0255-3

 

What's Happening?

Construction bids opened on 12-10-09 with apparent low bid of $6,545,157 by JFT Construction, Inc.

Construction is 16% complete as of progress meeting held on 06-02-10.

Construction started on 04-12-10 and it should be completed within 450 calendar days.

Construction kick off meeting held on 04-07-10.

City Council approved construction contract on 02-24-10.

Project Description

The project consists of storm sewer improvements including associated inlets, inlet leads, and laterals. The existing water lines throughout the project area will be upgraded and replaced. The pavement and sidewalks throughout the project area will be replaced in conjunction with a Neighborhood Street Reconstruction Project.



Last Updated 6/3/2010