Brays Bayou Detention Site

Complete
The project was awarded to the General Contractor on 10-24-2007.

General Contractor: BRH Garver
COH Construction PM: Joanne Kamman
SWMP Design Engineer: AECOM
Construction Contract: $5,484,362
CIP No.: M-0260-5

 

What's Happening?

Final inspection held on 02-19-2009.

Project Description

The project consists of construction of an approximately 200 ac-ft detention basin. A concrete weir installed at the common bank with Brays Bayou will control the flow of storm water into the basin from the bayou. The basin outfall restrictor is a 36-inch diameter storm pipe.

Last Updated 5/5/2009