Kirkwood Dr. from Memorial Dr. to IH-10, Woodthorpe Ln. from Kirkwood to Carlingford Ln., and Taylorcrest Rd. from Kirkwood to West Forest Dr. The project is located on Key Map 489A, E.
Under Engineering Design
SWMP Design Engineer: CivilTech Engineering Inc.
Construction Award: FY2012
Construction Estimate: $8,250,000
CIP No.: M-0247
90% Final Design on hold.
The project consists of the design of an 84-in diameter reinforced concrete storm pipe bored under Memorial to connect the new storm sewer along Kirkwood. From Kirkwood north to Kimberley a 9-ft X 7-ft reinforced concrete box storm sewer will connect to an existing 84-in diameter storm pipe from the west and transition to a 54-in diameter reinforced concrete storm pipe traveling north. A new 66-in diameter reinforced concrete storm pipe will be installed along Woodthorpe. A new 54-in diameter reinforced concrete storm pipe will be installed along Taylorcrest. New inlets will be installed at each cross street along Kirkwood. New 16-in diameter water line along Kirkwood. The roadway pavement will be reconstructed full width concrete with curb and gutter. The pavement on Kirkwood will be four-lane divided section with median including sidewalks.
Last Updated 6/26/2009