Kirby Drive Storm Sewer Relief - Phase 2

Under Construction
General Contractor: Pace Services L. P.
Constr Est: $10,923,847
COH Construction Project Manager: Joanne Kamman
SWMP Design Engr: AECOM
Constr Award: FY2009
CIP No.: M-0230

 

TBD: TBD

What's Happening?

Construction start date 08-17-2009 and it should be completed within 390 calendar days.

Construction progress is 59% complete as of meeting held on 04-29-10.

Project Description

This project consists of approximately 2,304 linear feet of 12-inch, 8-inch water lines, 12,970 linear feet of 96-inch, 90-inch, 84-inch, 72-inch, 60-inch, 48-inch, 42-inch, 36-inch, and 24-inch storm sewer, 8,193 linear feet of 21-inch, 15-inch, 10-inch, 8-inch sanitary sewer reconstruction/rehabilitation and concrete roadway reconstruction with curb and gutter.

Last Updated 5/21/2010