This project is generally bounded by Inwood on the North, Westheimer on the South, River Oaks Blvd on the West and Kirby Drive on the East. The project is located on Key Map 492 P,Q,T,U.
Under Construction
General Contractor: Pace Services L. P.
Constr Est: $10,923,847
COH Construction Project Manager: Joanne Kamman
SWMP Design Engr: AECOM
Constr Award: FY2009
CIP No.: M-0230
TBD: TBD
Construction start date 08-17-2009 and it should be completed within 390 calendar days.
Construction progress is 59% complete as of meeting held on 04-29-10.
This project consists of approximately 2,304 linear feet of 12-inch, 8-inch water lines, 12,970 linear feet of 96-inch, 90-inch, 84-inch, 72-inch, 60-inch, 48-inch, 42-inch, 36-inch, and 24-inch storm sewer, 8,193 linear feet of 21-inch, 15-inch, 10-inch, 8-inch sanitary sewer reconstruction/rehabilitation and concrete roadway reconstruction with curb and gutter.
Last Updated 5/21/2010