Lancaster Storm Sewer Relief Project

Complete
The project was awarded to the General Contractor on June 14, 2006.

General Contractor: Pace Services L.P.
COH Construction Project Manager: Salim Ayub
SWMP Design Engineer: Jaymark Engineers
Construction Contract: $9,717,726
CIP No.: M-0228

 

What's Happening?

Substantial completion inspection held on 09-29-2008.

Project Description

The project consists of the construction of approx. 13,101-linear ft. of 18-in. thru 78-in diameter storm pipe, asphalt roadway reconstruction with concrete curb and gutter, 30,560-linear ft. of 8-in. thru 16-in. diameter water line replacement, and 5,193-linear ft. of sanitary sewer rehabilitation. The project is partially funded by CDBG funds.

Last Updated 6/23/2009