The project area is generally bound by Crane St. on the north, Liberty Rd. on the south, Altoona/Hirsch Rd. on the west, and Kashmere St. on the east.
Storm Sewer Consolidated Construction Fund
Complete
The project was awarded to the General Contractor on June 22, 2005.
General Contractor: Bearden Contracting Co.
COH Construction Project Manager: Salim Ayub
SWMP Design Engineer: SES Horizon
Construction is complete.
This project consists of approximately 6,119 linear feet of 60-in., 54-in., 42-in., 36-in., 30-in., and 24-in. storm sewers, concrete curb and gutter roadway reconstruction, sidewalks, waterline and wastewater replacement. This project was partially funded by CDBG.