Sunnyside Court Storm Sewer Laterals Project

Complete
The project was awarded to the General Contractor on June 14, 2006.

General Contractor: E.P. Brady Ltd.
COH Construction Project Manager: Salim Ayub
SWMP Design Engineer: Weisser Engineering, Inc.
Construction Contract: $5,325,195
CIP No.: M-0217

 

What's Happening?

Project is complete

Project Description

The project consists of construction of approx. 627-linear ft of 4-ft X 2-ft reinforced concrete box storm sewer. Approx. 11,329-linear ft of 18-in thru 78-in diameter reinforced concrete storm pipe and ditch culverts with ditch regrading. The roadway pavement will be reconstructed full width with asphalt overlay and concrete curb and gutter. The project includes the construction of a detention basin between Mariah and Bassett. There is 2,649-linear ft of 8-in diameter sanitary sewer replacement along Brandon and 853-linear ft of 8-in diameter water line replacement at various locations.

Last Updated 10/29/2008